Seekh

Lessons learnt meeting page for the Special Towers Framework review. This HTML version keeps the deck content readable in the browser and preserves the PowerPoint download as the source file.

Meeting focus

Capture what happened, what the team learnt, and what needs to change for future special tower reviews.

Slide 01

KEC International Limited

Seekh Improvement #001 – Special Towers Framework (521)

Power T & D

Cables

Railways

Civil

Solar

Oil & Gas Pipelines

Slide 02

M521 review cycle

Timeline 1: 14 weeks of back-and-forth on what SEC asked at Rev 0. Timeline 3: Rev 4 converged with contract completion.

TIMELINES

TIMELINE 1 · Complied with SEC interpretation on the 4th cycle

KEC Stance

SEC Stance

  • Multi-pier design +
  • RQD averaging

Rev 0

13-Jan-26

Comments Rev 0

  • Flags RQD avg +
  • pile-length assumptions
  • Defends RQD avg via
  • geotech letter

Rev 1

~Feb

NOT COMPLIED

  • Flags safety-case
  • framing
  • Regroups G1/G2;
  • shear partial

Rev 2

~early-Mar

Partial

  • Shear method
  • still questioned
  • Argues shear
  • non-critical for OHTL

Rev 3

~early-Apr

NOT COMPLIED

  • 2 items NOT COMPLIED
  • — unfactored shear
  • Redesigned w/
  • FACTORED SHEAR

Rev 4

22-Apr-26

Pending approval

Awaiting decision

SITE EVENTS

4–5 Apr · Site cuts rebar at 1A/31 (bar-through-pile clash)

TIMELINE 2 Started Late

Contract start

6-Nov-2024

Rev 0 submitted

13-Jan-2026

~62 wks (~14 mo)

Rev 1 / 2 / 3

Feb–early-Apr

+~12 wks

Rev 4 filed

22-Apr-2026

~76 wks total

Contract completion

22-Apr-2026

⚠ same day

SEC COMMENTS (Rev 0) · complied at · days from comment receipt

SEC comment at Rev 0

Complied at

Days from receipt

RQD averaging — use POOREST borehole, not group-averaged (TES-P-122.06)

Rev 4 (22-Apr-26)

≈ 82 days

Unfactored shear on G1 + G2 — use FACTORED shear per ACI 318M

Rev 4 (22-Apr-26)

≈ 82 days

Pile-length assumptions need geotech-backed rework

Rev 2 (~early-Mar)

≈ 35 days

Slide 03

Learnings — what happened, how we close it

LESSONS

WHAT HAPPENED → CORRECTIVE ACTION

What happened on M521

Corrective action

Constructability

  • ▸ Design identifies special towers at tower-spotting freeze
  • ▸ Design reviews constructability on draft drawings (12-point)
  • ▸ PM verifies Rev 0 before release
  • Rev 0 → Rev 4 took 14 weeks
  • Rev 4 converged on SEC's Rev 0 position.

▸ SEC's preferred interpretation in Rev 0 for special towers (explore AI use cases)

Foundation work on special towers began late

  • ▸ Special towers tracked separately in Primavera P6
  • ▸ Front-load special-tower foundations along with the suspension batch

No first-of-its-kind verification was run for F-AN3/SPL.

  • ▸ BIM / digital-twin clash-check on cage geometry, or
  • ▸ Full-scale rebar mockup (borrowed from oil & gas practice)

Site cut rebar at 1A/31

▸ Strengthen Quality process to flag non-conformances

Slide 04

Constructability Check + Earmark Process for Special Towers

CONSTRUCTABILITY

STEP 1 — IDENTIFY · which towers get the special track, and when we earmark them

FLAG AS SPECIAL IF ANY:

  • ▸ F-AN3/SPL, F-DE, large-angle / "SPL" variant ▸ Deviation > 45° ▸ RQD < 25 in any critical layer, or rock interface < 3 m
  • ▸ Non-spread foundation (pile / multi-pier / raft) ▸ First-of-its-kind ▸ Sabkha, wadi crossing, sloped ground
  • EARMARK AT TOWER-SPOTTING FREEZE
  • (Month 1–3) — when tower types are
  • assigned in the schedule

STEP 2 — REVIEW · 12-point Constructability Checklist (signed item-by-item, pre-IFC)

1

Every bottom longitudinal bar crosses a pile footprint ← the 1A/31 miss

2

≥ 50 mm clear spacing between bars at pier edge

3

Top bars survive stub cutout without cutting

4

Development length Ld achievable at pier-to-pad

5

Bar bend points clear of stub flanges

6

Vibrator-diameter clearance between bars

7

Chair-bar spacing matches pile-cap depth

8

Temperature reinforcement in open pad area

9

Uplift-test pullout points accessible + instrumented

10

Formwork matches pier geometry; no reshaping at site

11

Construction sequence diagram shipped with drawing

12

No site cutting long-span bars (TES-P-122.06 · ACI 315/318)

STEP 3 — EXECUTE · post-earmark workflow - what we do after a tower is flagged

When

Action

AS-IS on M521 (what didn't happen)

Month 1

Design IDENTIFIES — flag at tower-spotting freeze; separate line in Primavera P6

F-AN3/SPL not earmarked; entered the special track late

Month 2

Design REVIEWS constructability — 12-point check on draft drawings

No constructability review; bar-through-pile on Rev 0 was not caught

Month 3–4

SUBMIT — Foundation Plan & Details to SEC (with risk-flag package)

Rev 0 for special towers filed 13-Jan-26, ~62 weeks (~14 months) after 6-Nov-24 kick-off

Month 5

PM VERIFIES Rev 0 — mandatory risk-flagging sheet signed

No single PM-owned verification; risks surfaced one revision at a time

Parallel

AMBITIOUS — BIM clash-check OR full-scale rebar mockup (first-of-its-kind)

Neither attempted; Stage D never run for F-AN3/SPL

Execution

Monthly Seekh review until first pile-cap poured; site changes auto-flag

1A/31 clash surfaced from the 1v1 on TSE release-risks — no NCR was raised

Slide 05

THANK YOU

  • Global Footprint in
  • 110+ countries*

*Includes EPC and Supply

www.kecrpg.com

Follow us on:

Slide 06

Back-up · SOW 24CO375 Foundation Checklist — sections II to VI

TES-P-122.06 · TCS-P-122.05/.21 · TCS-Q-113.03 · ACI 318M · IEEE 691-2001 · ASTM D1586/D2113/D3689

BACK-UP

II. FOUNDATION DESIGN

SOW Cl 5.11 · TES-P-122.06 · ACI 318M

▸ Design per ACI 318M + TES-P-122.06 — torsion, uplift, compression, shear, moments

▸ Type: drilled pier / spread / rock anchor / rock pier / driven pile

▸ Grouped towers: use POOREST borehole — no averaging

▸ Top 1.0 m soil EXCLUDED from uplift / compression / lateral

▸ Spread footing FoS ≥ 1.5 on uplift; OLF per Table-2

▸ Sabkha: 13 mm permanent steel casing, rebar hot-dip galv

III. SOIL INVESTIGATION

SOW Cl 6.21

▸ COMPANY-approved geotech; start after prelim proposal approval

▸ Borehole at EACH tower; depth ≥ (pier + 3 m) OR 10 m

▸ ASTM D1586 (SPT) + D2113 (diamond core drilling)

▸ FoS ≥ 3 on ALL soil parameters; COMPANY interprets

▸ ≥3 boreholes with 2″ PVC piezometers, depth ≥3 m

IV. REINFORCEMENT

SOW Cl 6.03 · TCS-P-122.05 · TCS-P-122.21

▸ Reinforcement + tie wire per TCS-P-122.05 / TES-P-122.06

▸ Tie wire 1.5 mm, 2 wraps + twists; 2 separate spliced ties

▸ WWF per ASTM A496 / SASO 224; fy ≥ 240 MPa

▸ Stub-angle bond per TCS-P-122.21; coal-tar + mastic tape

▸ No site cutting long-span bars without design authority

V. PROTOTYPE UPLIFT TEST — PRE-CONSTRUCTION GATE

SOW Cl 5.12

▸ Full-scale test: 1 tangent + 1 heavy-angle, BEFORE production

▸ Prototype design gated on APPROVED soil report

▸ COMPANY witnesses; contractor pays access

▸ Jacks / load cells / dial gauges calibrated w/ COMPANY

▸ Per ASTM D-3689-90 quick-load method

VI. CONSTRUCTION QUALITY CONTROL

SOW Cl 4.87 · 6.02 · 6.25

▸ Checklists define HOLD / WITNESS / SURVEILLANCE

▸ Pre-pour inspection mandatory; request → COMPANY

▸ Cover 85 ± 10 mm to tie outside; design 95 mm

▸ CIP concrete per TCS-Q-113.03 + TCS-P-122.05

▸ Inspection logbook; results stored / retrievable

KEY GATES — what stops the line if missed

cross-cuts the five sections

▸ No averaged RQD across grouped towers — use poorest

▸ Soil APPROVED before prototype design starts

▸ Uplift test (1 tangent + 1 heavy-angle) BEFORE production

▸ No long-span bar cutting without design authority

▸ Pre-pour HOLD request to COMPANY

▸ Drawings + material: only after IFC, certified + dated

GATE: no IFC, no material — until II–VI are signed off on project-specific soil data.

Slide 07

Back-up · 12-point Constructability Checklist — each item explained

Plain-language meaning + source (ACI / TES-P / SOW clause) for every checkpoint. A synthesis, not a published list.

BACK-UP

1

Bottom longitudinal bar crosses a pile footprint

Every bottom longitudinal bar must be routed so its path crosses the footprint of at least one pile; otherwise the bar cannot transfer tower load and is structurally dead. The 1A/31 failure was bars exiting the pier edge without crossing a pile.

1A/31 failure mode itself

2

≥ 50 mm clear spacing between bars at pier edge

50 mm is the practical OHTL-foundation minimum because a 40–55 mm poker vibrator needs clearance to consolidate concrete between bars. Tighter = honeycombing = a hidden defect.

ACI 318 §25.2

3

Top bars survive the stub cutout without cutting

The top reinforcement mat has a cutout to let the vertical stub pass. Top bars near that cutout must be routed so they do not need to be cut at site; if cut, they lose structural function at the cutout zone.

ACI 315/318 · TES-P-122.06

4

Development length Ld achievable at pier-to-pad

At the transition from narrow pier to wide pad, bars change direction (L-hooks / 90° bends). Each bar must have enough straight length + bend to reach full Ld before termination; else the bar pulls out under load.

ACI 318 §25.4

5

Bar bend points clear of stub flanges

Tower stubs carry horizontal flange plates. A bar bend-radius arc must not clash with a flange; if it does, placement is impossible without shop-cutting the flange — 3D clash must be checked before drawing goes IFC.

Pre-IFC 3D clash check

6

Vibrator-diameter clearance between bars

Immersion concrete vibrators are ~50 mm diameter. Bars must allow vibrator insertion throughout the cage depth; congestion leaves un-vibrated concrete pockets — voids / capacity loss invisible from outside.

Site constructability

7

Chair-bar spacing matches pile-cap depth

Chair bars hold the upper mat at design elevation during the pour. Spacing must be calibrated to cap depth and steel weight — too wide = mat deflects and ends up at wrong elevation; too tight = congestion.

Rebar placement practice

8

Temperature reinforcement in open pad area

Large open concrete areas need nominal reinforcement to control cracking from thermal contraction + shrinkage, independent of structural load. Easy to miss in OHTL drawings because load concentrates at piers, not pad.

ACI 318 §24.4

9

Uplift-test pullout points accessible + instrumented

SOW §5.12 mandates a full-scale uplift test on one tangent + one heavy-angle prototype. The prototype must have physical anchor points for hydraulic jacks + dial gauges designed into the rebar layout — afterthought = drilled post-cure = compromised test.

SOW 24CO375 §5.12

10

Formwork matches pier geometry; no reshaping at site

Formwork must be fabricated to match design pier geometry exactly (tapered, multi-step). If site must cut / rework formwork to fit the drawing, dimensional accuracy of the finished concrete and rebar cover suffers.

Site constructability

11

Construction sequence diagram shipped with drawing

Shows order of operations: excavation → lean concrete → bottom mat → chair bars → top mat → stub setting → formwork → pour → cure. Without it, each crew interprets differently and sequence errors cascade into rebar conflicts like 1A/31.

Standard OHTL drawing practice

12

No site cutting of long-span bars

Longitudinal bars carry the primary structural load; cutting them at site without design authority is prohibited. If a bar does not fit, the drawing must be revised and re-approved before placement proceeds. This was the SEC-consultant flag at 1A/31.

TES-P-122.06 · ACI 315/318

Slide 08

Back-up · Site + Jawda Track (parallel to the SEC cycle in April)

The day-by-day scramble on the 1A/31 fix — back-up detail for the Timeline-1 story on the front page.

BACK-UP

TIMELINE 2 · Site + Jawda Track · April 2026

4–5 Apr

  • Site cuts rebar 1A/31
  • (bar-through-pile)

9 Apr

  • Faisal (Technotran):
  • service-moment justification

13–16 Apr

  • Zafery chases Jawda
  • 6× over 5 days

16 Apr

  • Jawda letter issued —
  • generic, needs rework

19 Apr

  • 1v1 on TSE release-risks:
  • 2 gridlocked, 2 retrofit

24 Apr

  • Concrete pour scheduled
  • (pending revised letter)

POSITIONS · KEC solution · SEC stance · why the Jawda letter needs a re-issue

  • KEC SOLUTION (current path):
  • ▸ 2-vs-2 fix split. 1A/31 + 1B/31 on site-cut + Faisal service-moment + revised Jawda letter.
  • ▸ 1A/32 + 1B/32 on clean retrofit (+2.3 T extra rebar). Rev 4 with factored shear filed 22-Apr.
  • SEC STANCE (consistent across 14 weeks):
  • ▸ No unfactored shear on OHTL foundation reinforcement (ACI 318M).
  • ▸ No averaged RQD where individual layers read 0 or < 10.
  • ▸ No rebar cutting without Designer + Approved-Designer letter (TES-P-122.06).
  • WHY THE 16-APR JAWDA LETTER NEEDS A RE-ISSUE:
  • ▸ Generic scope — did not name all 4 locations. Did not address top-bar cutting at the stub.
  • ▸ Wrong factor-of-safety framing. Needed further markup; still being closed as of 23-Apr.
  • ▸ Revised letter to align with the 19-Apr 4-point site-feasibility proposal before the pour.