Changes with month/project filters. Shows how much is ready based on tower erection.
| Project | Towers | % Fdn | % Pile Cap | % Erected | % Cond PO | Stringable (km) | Sections Ready |
|---|
Each tile is clickable. Click to see full detail table. Click outside popup to close.
% Towers Complete = completed towers ÷ total towers. % Sections Stringable = fully-ready sections ÷ total sections. Responds to project filter.
Isolates the effect of angle tower non-readiness on the Erection Completion basis. Has its own month slider below — independent of the filters above.
Average days between milestone completions, grouped by tower type. Independent filters below — does not follow the global As-On / Project filters.
| Tower Type | Towers | → | n | → | n | → | n | → | n |
|---|
Average turnaround days by month (based on the "To" activity date). Shows whether cycle times are improving or degrading over time. A flat overall average can hide a worsening or improving trend.
Full sequential milestone chain (CS → SI → AR → ... → CJC). Each cell shows average days for that transition. The slowest transition per tower type is highlighted in red as the bottleneck. Only transitions with data (n ≥ 1) are shown.
Percentage of towers that have a completion date recorded for each milestone, grouped by tower type. Towers with any date (including same-day) are counted as complete.
| Tower Type | Towers | Foundation Concreting | Done | Pile Cap | Done | Tower Erection | Done | OPGW PO | Done | Conductor PO | Done |
|---|
Average calendar days between any two milestone dates, per project. Select projects, pick From & To activities, and the table updates instantly. Towers with missing/non-date values for either activity are excluded.
| Project | Avg Turnaround (days) | Towers (n) |
|---|
Full scope of all projects. Span = sum of section spans (angle-to-angle stretches). Towers = count from raw data.
| Project | Total Towers | Angle Towers | Suspension Towers | Sections | Total Span (km) |
|---|